Weekly reports and decisions

Team leads · analysts · project and operations managers

A report that separates recorded progress, risks, decisions needed and the next step.

Red flag to catch: The report says “on track”, cites a percentage or claims approval without evidence, or the manager’s review is written as an approval.

Module 04Weekly reports and decisions
Recorded progress
site measurement completed (work notes, Monday).
AI draftMaterial supply is complete.
Stopped work and why
Risks
Next week
No confirmed start date is recorded.
Decision needed
Owner: not stated; needs confirmation.
Delivery note
3 material items reached site.
1 item missing; supplier said "next week".
INTERNAL DRAFT · NOT SENT
DOCUMENTS ARE FICTIONAL

THE CASE IN THIS MODULE

The situation you work on

Fictional work notes, a delivery note and a risk list give partial evidence. The records deliberately contain no completion percentage; any percentage in a draft is unsupported. The manager reviews the draft on four points before it leaves the team and writes down what they found; the review is never an approval.

WHAT YOU DO

  1. Write only the progress sentences the records support, with their source.
  2. Write each risk in the risk list’s own words; where its impact, owner or date is not in the record, say “needs confirmation”.
  3. For next week, write dependencies, not dates; pull each decision and its owner onto its own line.
  4. Give the draft to your manager; the manager writes findings back, which is not an approval.